Smithfield's Market Tunnel Upgrade

Steel support install

1. Installation of additional support steels in the underground arches below Smithfield's market 2. The steel weight 3200kgs 6m in length had to be turned behind the existing columns and lifted up into position using the pick and carry crane with hydraulic searcher hook. 3. To carry out the installation we required a hydraulic gantry & counterbalance forklift as well as the pick and carry crane all lifting steel components to complete the install.